Happy Saturday, Silver Trout! Here is what is going on at the development,
- Lots 9 & 10: Siding install is still in progress. Rough plumbing and electrical are in progress.
- Lots 11 & 12: Insulation to begin next week as well as stone install.
- Lots 13 & 14: Slab prep and underslab insulation is complete. In floor heat to start early next week followed by slab pour.
Enjoy your weekend!