Buyer Update April 10th, 2021

April 10, 2021 by Waters at Silver Trout

A home with a view

Good afternoon, here’s what’s been happening around the neighborhood this week:

  • Lots 9 & 10: Roughs to be finished next week followed shortly after by insulation.
  • Lots 11 & 12: Insulation is nearing completion on Unit 11. Drywall has been hung in Unit 12.
  • Lots 13 & 14: Truss installation has begun. Roof to be complete and ready for dry in next week.
Enjoy the weekend!

Photo Gallery

Front siding going on
Unpacking the details in the basement
Custom standup shower
Great room drywall
Framing going up 1

Filed Under: News

Buyer Update April 3rd, 2021

April 3, 2021 by Waters at Silver Trout

All insulated up

Good afternoon, Waters at Silver Trout! Here’s what’s been happening around the neighborhood this week:

  • Lots 9 & 10: Siding install is nearing completion.  Rough inspections are scheduled for next week.
  • Lots 11 & 12: Insulation will be complete next week.  Gypcrete has been poured, and drywall was delivered in unit 12.
  • Lots 13 & 14: First floor framing is complete. Second floor framing is nearing completion. Trusses will be delivered next week.
Enjoy the beautiful spring weather this weekend!

Photo Gallery

Framing going up Framing from the inside Siding going on

Filed Under: News

Buyer Update March 20th, 2021

March 20, 2021 by Waters at Silver Trout

mbs team photo

Waters at Silver Trout Neighborhood,

We are sorry to have to share with you that Paul passed away last night in a sudden turn in his battle with cancer. We are deeply saddened and will miss his sarcastic humor, endless energy, and enthusiasm. Matty and I were with family at his side and he is in a better place right now.

Due to this news, we do not have a written update this week. Please enjoy these photos. If you would like an update on your unit, please reach out to your real estate broker. Updates will proceed as normal next week. Thank you for your understanding.

Photo Gallery

Interior picture windows
Exterior framing going up
Garage doors
Buffalo in the distance

Filed Under: News

Buyer Update March 13th, 2021

March 13, 2021 by Waters at Silver Trout

Exterior finishings

Happy Saturday, Waters at Silver Trout.

  • Lots 9 & 10: Siding install is still in progress. Rough plumbing passed inspection this week. Rough electrical to be finished next week.
  • Lots 11 & 12: Insulation is still in progress. Services to the house have been trenched and installed.
  • Lots 13 & 14: Framing has begun. First floor is near completion and the floor has begun to be installed.

Enjoy your weekend!

Photo Gallery

Windows
Doors coming in
Framing structure going up
Tyvek going on
Fireplace framed in
Siding going up

Filed Under: News

Buyer Update March 6th, 2021

March 6, 2021 by Waters at Silver Trout

Tyvek exterior

Happy Saturday, Waters at Silver Trout.

  • Lots 9 & 10: Siding install is still in progress. Rough plumbing and electrical in progress.
  • Lots 11 & 12: Insulation continues this week. Drywall to begin next week.
  • Lots 13 & 14: Concrete slab what’s been poured. First floor framing to start next week

Enjoy your weekend!

Photo Gallery

Shower framed in
Concrete basement
Dryed in interior
Corner windows
Exterior siding going on

Filed Under: News

Buyer Update February 27th, 2021

February 27, 2021 by Waters at Silver Trout

Exterior getting insulated

Happy Saturday, Silver Trout! Here is what is going on at the development,

  • Lots 9 & 10: Siding install is still in progress. Rough plumbing and electrical are in progress.
  • Lots 11 & 12: Insulation to begin next week as well as stone install.
  • Lots 13 & 14: Slab prep and underslab insulation is complete. In floor heat to start early next week followed by slab pour.

Enjoy your weekend!

Siding going on 1

Filed Under: News

Next Page »

© 2021 Silver Trout Estates

The developer reserves the right to change interior and exterior finishes.

Sotheby’s International Realty® and the Sotheby’s International Realty Logo are service marks licensed to Sotheby’s International Realty Affiliates LLC and used with permission. LIV Sotheby’s International Realty fully supports the principles of the Fair Housing Act and the Equal Opportunity Act. Each franchise is independently owned and operated. Any services or products provided by independently owned and operated franchisees are not provided by, affiliated with or related to Sotheby’s International Realty Affiliates LLC nor any of its affiliated companies.